![]() |
||||||||||
|
From the Director: Flood!It wasn't biblical in proportions, and it didn't do nearly as much damage as it might have, but it did serve, in more ways than one, as a wake-up call. About 4:30 in the morning of Monday, March 5, a sprinkler head in the fire suppression system burst on tier 9, in Bancroft's "attic," space used to store supplies as well as to stage incoming archival collections while they await processing. This released a steady stream of water which dripped down over cartons with an unprocessed collection, then puddled underneath the shelving, and eventually found its way through the floor and into ventilation ducts. At the same time, it set off a flow alarm that brought the Berkeley Fire Department to the scene along with campus emergency personnel. Unfortunately, since the flow alarm is indistinguishable from a fire alarm, and they found no evidence of fire, they assumed that Bancroft had had a false fire alarm. It was not until just over two hours later, when Bancroft staff member Wayne Silka came in at 6:45 a.m. to begin his normal routine of checking the building that the water was discovered. By that time it was standing two inches deep in the offices of the Mark Twain Project and in the Library Systems Office directly beneath and had begun to seep through the ceiling of the Heller Reading Room.
Wayne immediately set standard Bancroft security procedures in motion, calling me and other Bancroft staff, the Library Security Office, Barclay Ogden, Head of the Library Conservation Department, and campus facilities management staff. After the sprinkler system was shut down, it took about twenty-five Bancroft, Library, and campus staff just over three hours to vacuum up the standing water and bring in dehumidifiers and powerful fans to dry the building out, a process that continued for several days. About fifty cartons of archival materials waiting for processing were damaged, although in most cases the waxed surface of the cartons preventing water from reaching more than the outside edges of the documents they contained. Thanks to contingency arrangements with local frozen food storage facilities, these damaged cartons were freeze-dried the same day. This is a crucial step in recovering from water damage. If water soaked materials are not frozen within 48 hours, fungus and mold create irreparable damage to the paper. Over the past several months, as time and staffing in the Library Conservation permit, we have systematically removed these materials from cold storage in order to treat them as necessary. In most cases no conservation work has been needed at all. About three weeks after the first sprinkler head burst, a second one failed, on tier 7. Fortunately, the leak was discovered almost immediately, and little damage was done. At this point we appealed to Ron Coley, Associate Vice Chancellor for Business and Administrative Services, for help. It was clear that if sprinkler heads continued to burst at this rate, Bancroft's collections would be seriously at risk. A little research revealed that the sprinkler heads in the Doe Annex, the building that houses Bancroft, were almost thirty years old and at the end of their useful life. Vice Chancellor Coley needed little convincing that it was time to replace all of the sprinkler heads, which would cost approximately $50,000. Fortunately the campus was able to fund the replacement with deferred maintenance funds.
|
Volume 119
|
|||||||||
![]() |
||||||||||
![]() |
![]() |
|||||||||
|
Bancroft
Home
|
General
Information
|
Collections
|
Research
Programs
|
|
Reference
and Access Services
|
News,
Events, Exhibitions, Publications
|
|
Friends
of The Bancroft Library
|
Site
Map
|
Search
The Bancroft Library Website
|
|
UC Berkeley
Library Home
|
Catalogs
|
Search
the Library Website
|
Copyright (C) 2005 The Regents of the University of California. All rights reserved.
Document maintained by The Bancroft Library.
Last update 08/08/05. Server manager: Contact